13605B Folsom Road

Construction Updates

December 2025 Construction Updates

Recent Activities:

  • Overhead power relocation efforts have continued with wires being pulled into place. Electrical line installation will continue until it is completed.

  • The sewer extension along the north side of Folsom Road is under construction.

  • Excavation of the Shields Brook Stormwater Treatment Site, including required blasting, is complete.

  • Installation of humus and stone has begun in the Shields Brook Stormwater Treatment Site.

  • Madden Road was paved along with completed parts of Folsom Road between Franklin Street and Laconia Avenue.

  • Deck forms have been removed from the underside of the bridge.

Upcoming Activities:

  • Power work at American Excavating is anticipated to be completed in the first 2 weeks of December.

  • Full power relocation efforts are expected to be complete by the end of December.

  • Temporary paving of Franklin Street Extension will take place as soon as possible in December.

  • The installation of sewer will continue along the North side of Folsom.

  • Sewer work on Folsom Road will start at the Franklin Street intersection and move east towards Rt 28.

November 2025 Construction Updates

Recent Activities:

  • Overhead power relocation efforts have continued with wires being pulled into place, and will continue until complete.

  • Waterlines throughout Phase 1 are being installed and pressure tested.

  • Gas line relocation on Folsom Road is complete.

  • The cap for the Northwest MSE Wingwall has been installed.

  • Form work for the Shields Brook Bridge deck was completed, shear connectors were installed, and deck reinforcing was installed and approved.

  • The deck placement for Phase 1 occurred on the 28th of October.

  • Sewer work at Franklin Extension intersection has begun.

Upcoming Activities:

  • The closure placement, sidewalk and median curb are anticipated early November.

  • Power relocation efforts are anticipated to be complete by the end of the month.

  • Paving of Madden Road and completed parts of Folsom Road will take place in early November.

  • The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).

  • Water main installation on North High Street will continue.

  • Sewer work on Folsom will start at the Franklin intersection and move east towards Route 28.

October 2025 Construction Updates

Recent Activities:

  • Steel girders for Phase 1 were set in the last two weeks of September.

  • Overhead power relocation efforts have continued with new poles installed throughout the jobsite. Electrical line installation has begun and will continue until completed.

  • Waterlines throughout Phase 1 are installed and being pressure tested.

  • Gas line relocation on Folsom Road is ongoing.

  • The MSE Wingwall for the Northwest corner of the bridge has been installed.

  • Bolt tensioning has been completed

  • Both abutments were backfilled to the height of the bridge seats.

  • Forming for the deck concrete has commenced and will continue until complete.

Upcoming Activities:

  • Work on form installation for the bridge deck will continue until complete.

  • Deck studs will be installed next week.

  • Rebar installation will commence once forming and studs are complete.

  • The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).

  • Water main installation on North High Street will continue.

  • Paving of Madden Road and Folsom for Phase 1 between the bridge and carwash is anticipated during the month of October. 