13605B Folsom Road
Construction Updates
September 2025 Construction Updates
Recent Activities:
Shields Brook Bridge eastern abutment, Phase 1, concrete was finished.
Overhead power relocation efforts have begun with the drilling for new poles and line relocations on Madden Road.
Blasting continues along North High Street for drainage and waterline.
Gas Line relocation on Folsom Road is ongoing.
Construction of the stormwater treatment site opposite Manchester Avenue was completed.
Work on the northwest wingwall has begun.
Upcoming Activities:
Work on Phase 1 of the eastern abutment will continue until it is completed.
The installation of drainage and waterline will continue where permitted by the New Hampshire Department of Transportation (NH DOT).
Installation of structural steel is anticipated in September.
Drainage and waterline installation will continue on North High Street.
Paving will begin on Madden Road.
August 2025 Construction Updates
Recent Activities:
Blasting has been substantially completed in the stormwater treatment site opposite Manchester Avenue, with only work on the outlet remaining.
Shields Brook Bridge eastern abutment phase 1 concrete has begun.
Sand and crushed Stone have been installed on Folsom Road Phase 1.
The 12” waterline across Shields Brook has been installed and connected to the existing main.
Water main work along Folsom Road continued and is complete from Franklin Street to Lacona Avenue.
Blasting along Folsom Road for drainage and waterline continued.
Upcoming Activities:
Blasting along Folsom Road will continue for drainage and waterline work.
The new 12” waterline across Shields Brook will be pressurized to assist in water delivery for the Town.
The stormwater treatment site opposite Manchester Avenue will be excavated to grade and construction of the final configuration will begin.
Construction of the Northwest MSE Wingwall will begin.
Work on Phase 1 of the eastern abutment will continue until completed.
Utility relocations are expected to begin the second week of August, beginning at the Folsom Rd./NH Route 28 intersection.
Installation of drainage and waterline will continue.
Installation of structural steel at the Shields Brook bridge is anticipated to begin in September.
July 2025 Construction Updates
Recent Activities:
Blasting has continued in the stormwater treatment site opposite Manchester Avenue above the elevation of the access road.
The western abutment phase 1 concrete is complete and awaiting mechanically stabilized earth (MSE) wall construction.
Sand and crushed stone have been installed on Folsom Road between Manchester Ave and Laconia Ave.
The Shields Brook stormwater basin site is complete and awaiting drainage to be connected.
The multi use trail from north of the Shield Brooks Bridge to just north of Haley Drive has been excavated to subgrade.
Water Main work along Folsom Road was started excluding the parcel 63 area.
Blasting along Folsom road for drainage and waterline continued.
All drilled shafts for phase 1 have been completed.
Upcoming Activities:
Blasting will continue in the stormwater treatment site.
A 12” waterline will be installed across Shields Brook in phases due to an inability to directionally drill the waterline.
Select material installation will continue where subgrade is approved by the New Hampshire Department of Transportation.
Construction of the north west MSE Wingwall will commence.
Work on phase 1 of the eastern abutment will begin and continue until completed.
Eversource’s contractor is anticipated to be on site in the near future.
A storage tank will be installed at parcel 63 to facilitate the removal of the existing sewer line.
Work for Madden road is on hold until the utility pole can be relocated.
Installation of drainage and waterline will continue in areas permitted by the New Hampshire Department of Transportation.