New Hampshire Department of Transportation logo and project image.

13065B Folsom Road

Construction Updates

March-April-May 2026 Construction Updates

Recent Activities

  • Excavation in front of the Royal T Carwash.

  • Brought in and laid down high quality fill material on Folsom Road between Manchester Avenue and Route 28.

  • Placed drainage and waterline to the intersection of Route 28 and Folsom Road.

  • Installing temporary signals at the intersection of Route 28 and Folsom Road.

Upcoming Activities

  • Install drainage to bypass the box culvert.

  • Finish Crown Castle utility relocation.

  • Pave Folsom Road between Manchester Avenue and Route 28.

  • Pour approach slabs for the bridge over Beaver Brook.

  • Place embankment on Old Rum Trail to adjust to new roadway profile.

February 2026 Construction Updates

Recent Activities

  • Eversource completed their new line relocation.

  • FirstLight relocated their utility lines.

Upcoming Activities

  • Contractor has scaled back operations due to winter shutdown.

  • Utility work continues with relocation of signal power feed, relocation of the town fiber network, and FirstLight splicing cables.

January 2026 Construction Updates

Recent Activities

  • Overhead power relocation efforts have continued, with wires being pulled into place. Eversource should finish in early January.

  • Comcast relocated their lines to American Excavating; this will enable the construction of Old Rum Trail in this area. 

  • Installation of humus and stone has finished in the Shields Brook Stormwater Treatment Site.

  • Paving for Franklin Street Extension trenches was completed.

Upcoming Activities

  • Water line work on North High Street to Haley Drive.

  • Contractor has scaled back operations due to winter shutdown.

Construction Photos

If you would like to print this page, please click the button below.