13605B Folsom Road

Construction Updates

November 2025 Construction Updates

Recent Activities:

  • Overhead power relocation efforts have continued with wires being pulled into place, and will continue until complete.

  • Waterlines throughout Phase 1 are being installed and pressure tested.

  • Gas line relocation on Folsom Road is complete.

  • The cap for the Northwest MSE Wingwall has been installed.

  • Form work for the Shields Brook Bridge deck was completed, shear connectors were installed, and deck reinforcing was installed and approved.

  • The deck placement for Phase 1 occurred on the 28th of October.

  • Sewer work at Franklin Extension intersection has begun.

Upcoming Activities:

  • The closure placement, sidewalk and median curb are anticipated early November.

  • Power relocation efforts are anticipated to be complete by the end of the month.

  • Paving of Madden Road and completed parts of Folsom Road will take place in early November.

  • The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).

  • Water main installation on North High Street will continue.

  • Sewer work on Folsom will start at the Franklin intersection and move east towards Route 28.

October 2025 Construction Updates

Recent Activities:

  • Steel girders for Phase 1 were set in the last two weeks of September.

  • Overhead power relocation efforts have continued with new poles installed throughout the jobsite. Electrical line installation has begun and will continue until completed.

  • Waterlines throughout Phase 1 are installed and being pressure tested.

  • Gas line relocation on Folsom Road is ongoing.

  • The MSE Wingwall for the Northwest corner of the bridge has been installed.

  • Bolt tensioning has been completed

  • Both abutments were backfilled to the height of the bridge seats.

  • Forming for the deck concrete has commenced and will continue until complete.

Upcoming Activities:

  • Work on form installation for the bridge deck will continue until complete.

  • Deck studs will be installed next week.

  • Rebar installation will commence once forming and studs are complete.

  • The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).

  • Water main installation on North High Street will continue.

  • Paving of Madden Road and Folsom for Phase 1 between the bridge and carwash is anticipated during the month of October. 

September 2025 Construction Updates

Recent Activities:

  • Shields Brook Bridge eastern abutment, Phase 1, concrete was finished.

  • Overhead power relocation efforts have begun with the drilling for new poles and line relocations on Madden Road.

  • Blasting continues along North High Street for drainage and waterline.

  • Gas Line relocation on Folsom Road is ongoing.

  • Construction of the stormwater treatment site opposite Manchester Avenue was completed.

  • Work on the northwest wingwall has begun.

Upcoming Activities:

  • Work on Phase 1 of the eastern abutment will continue until it is completed.

  • The installation of drainage and waterline will continue where permitted by the New Hampshire Department of Transportation (NH DOT).

  • Installation of structural steel is anticipated in September.

  • Drainage and waterline installation will continue on North High Street.

  • Paving will begin on Madden Road.