November 2025 Construction Updates
Recent Activities:
Overhead power relocation efforts have continued with wires being pulled into place, and will continue until complete.
Waterlines throughout Phase 1 are being installed and pressure tested.
Gas line relocation on Folsom Road is complete.
The cap for the Northwest MSE Wingwall has been installed.
Form work for the Shields Brook Bridge deck was completed, shear connectors were installed, and deck reinforcing was installed and approved.
The deck placement for Phase 1 occurred on the 28th of October.
Sewer work at Franklin Extension intersection has begun.
Upcoming Activities:
The closure placement, sidewalk and median curb are anticipated early November.
Power relocation efforts are anticipated to be complete by the end of the month.
Paving of Madden Road and completed parts of Folsom Road will take place in early November.
The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).
Water main installation on North High Street will continue.
Sewer work on Folsom will start at the Franklin intersection and move east towards Route 28.
October 2025 Construction Updates
Recent Activities:
Steel girders for Phase 1 were set in the last two weeks of September.
Overhead power relocation efforts have continued with new poles installed throughout the jobsite. Electrical line installation has begun and will continue until completed.
Waterlines throughout Phase 1 are installed and being pressure tested.
Gas line relocation on Folsom Road is ongoing.
The MSE Wingwall for the Northwest corner of the bridge has been installed.
Bolt tensioning has been completed
Both abutments were backfilled to the height of the bridge seats.
Forming for the deck concrete has commenced and will continue until complete.
Upcoming Activities:
Work on form installation for the bridge deck will continue until complete.
Deck studs will be installed next week.
Rebar installation will commence once forming and studs are complete.
The installation of sewer and waterline will continue in areas permitted by the New Hampshire Department of Transportation (NH DOT).
Water main installation on North High Street will continue.
Paving of Madden Road and Folsom for Phase 1 between the bridge and carwash is anticipated during the month of October.
September 2025 Construction Updates
Recent Activities:
Shields Brook Bridge eastern abutment, Phase 1, concrete was finished.
Overhead power relocation efforts have begun with the drilling for new poles and line relocations on Madden Road.
Blasting continues along North High Street for drainage and waterline.
Gas Line relocation on Folsom Road is ongoing.
Construction of the stormwater treatment site opposite Manchester Avenue was completed.
Work on the northwest wingwall has begun.
Upcoming Activities:
Work on Phase 1 of the eastern abutment will continue until it is completed.
The installation of drainage and waterline will continue where permitted by the New Hampshire Department of Transportation (NH DOT).
Installation of structural steel is anticipated in September.
Drainage and waterline installation will continue on North High Street.
Paving will begin on Madden Road.