13065B Folsom Road
Construction Updates
May 2026 Construction Updates
Recent Activities
Muck and unsuitable excavation in front of the Royal T Carwash.
Placed selects on Folsom Road between Manchester Avenue and Route 28.
Placed drainage waterline to the intersection of Route 28 and Folsom Road.
Installing temporary signals at the intersection of Route 28 and Folsom Road.
Upcoming Activities
Drainage to bypass the box culvert.
Finish Crown Castle Utility relocation.
Pave Folsom Road between Manchester Avenue and Route 28.
Pour approach slabs for the bridge over Beave Brook.
Placing embankment on the Old Rum Trail to adjust to new roadway profile.
February 2026 Construction Updates
Recent Activities
Eversource completed their new line relocation.
FirstLight relocated their utility lines.
Upcoming Activities
Contractor has scaled back operations due to winter shutdown.
Utility work continues with relocation of signal power feed, relocation of the town fiber network, and FirstLight splicing cables.
January 2026 Construction Updates
Recent Activities
Overhead power relocation efforts have continued, with wires being pulled into place. Eversource should finish in early January.
Comcast relocated their lines to American Excavating; this will enable the construction of Old Rum Trail in this area.
Installation of humus and stone has finished in the Shields Brook Stormwater Treatment Site.
Paving for Franklin Street Extension trenches was completed.
Upcoming Activities
Water line work on North High Street to Haley Drive.
Contractor has scaled back operations due to winter shutdown.