Monthly Construction Updates

March Construction Updates

Recent Activities:

• Drainage was installed on Old Rum Trail.

• Drilled shafts, post and panels were installed for the southbound on ramp.

• Drilled shafts are being installed for the southbound on ramp as well as post and panels.

• Bridge form work is ongoing in preparations for concrete deck panels.

• Installation of the 60” round concrete pipe and headwall has been completed.

Upcoming Activities:

• Soundwall construction continues along southbound I-93. Towards the end of the month crews will relocate to the northbound wall to finish the remaining wall work.

• Drainage installation on Old Rum Trail will continue.

• Crews will set bridge deck panels in early April followed by shear studs.

• Signal/Intelligent Transportation Systems conduit is being installed on the new bridge.

• Contractor is actively hauling in select materials to the stockpile.

• Extra work for the Woodmont utility sleeves will take place this month.

• Signal foundations are being constructed for the northbound on/off ramp intersection.

March Construction Photos

February Construction Updates

Recent Activities:

• Drainage is being installed on Old Rum Trail.

• Soundwall construction on the southbound off ramp has finished.

• Drilled shafts are being installed for the southbound on ramp as well as post and panels.

• Bridge form work is ongoing in preparations for concrete deck panels.

Upcoming Activities:

Soundwall construction continues through the remainder of the winter on southbound. Wall post and panels are to be erected on southbound.

• Drainage installation on Old Rum Trail will continue.

• Bridge deck forming will continue.

• Installation of a 60” reinforced concrete pipe and headwall will take place this month.

• Blasting for stormwater best management practices and extra work for Woodmont utility sleeves will take place.

January Construction Updates

Recent Activities:

• Drainage is being installed on Old Rum Trail.

• Soundwall construction on the southbound off ramp has finished.

• Drilled shafts are being installed for the southbound on ramp as well as post and panels.

• Bridge girders have been installed and bolts tightened.

Upcoming Activities:

• Soundwall construction continues through the remainder of the winter on southbound. Wall post and panels are to be erected on southbound.

• Drainage installation on Old Rum Trail will continue.

• Bridge work has stopped for the month until the weather allows the setting of deck panels.

• Soil and stone work will take place on the southbound on ramp.

December Construction Updates

Recent Activities:

  • Excavation and Blasting for best management practices.

  • Drainage is being installed on Old Rum Trail.

  • Soundwall construction has continued along the southbound off-ramp.

  • Bridge girders have been installed.

Upcoming Activities:

  • Soundwall construction continues through the remainder of the winter on the southbound side of I-93. Wall post and panels are also to be erected on the southbound side of I-93.

  • Drainage installation on Old Rum Trail will continue.

  • Bridge crews will work on tightening bolts.

December Construction Photos

November Construction Updates

Recent Activities:

  • Old Rum Trail is currently receiving sand and crushed stone.

  • Drainage is being installed on Old Rum Trail.

  • Soundwall construction has continued along the northbound on-ramp.

  • Drilled shafts are being installed for the soundwall along the southbound on-ramp.

  • Paved base and binder on the northbound on and off ramps.

Upcoming Activities:

  • Soundwall construction continues through the remainder of the season on the northbound side of I-93. Wall posts and panels are to be erected in early to mid-December.

  • Drainage installation on Old Rum Trail will continue.

  • Girder erection is anticipated for mid-December.

November Construction Photos


If you would like to print this page, please click the button below.